We are performing a datacenter migration in Singapore, relocating some of our older hardware to a new facility where our newer servers are already operational. To minimize disruption, the migration will be carried out in batches during local nighttime hours.
📅 Migration Schedule (SGT - Singapore Time, UTC+8)
March 5, 2025 | 00:00 - 08:00
- SGP-DP-H11
- SGP-DP-H13
- SGP-DP-H10
- SGP-DP-H18
March 6, 2025 | 00:00 - 08:00
- SGP-DP-H14
- SGP-DP-H15
March 8, 2025 | 00:00 - 08:00
- SGP-DP-H06
- SGP-DP-H07
- SGP-DP-H08
- SGP-DP-H09
March 9, 2025 | 00:00 - 08:00
- SGP-DP-H12
March 10, 2025 | 00:00 - 08:00
- SGP-DP-H24
- SGP-DP-H25
- SGP-DP-H26
- SGP-DP-B26
March 12, 2025 | 00:00 - 08:00
- SGP-DP-H22
March 13, 2025 | 00:00 - 08:00
- SGP-DP-H19
- SGP-DP-H20
- SGP-DP-H21
- ROUTER-01
March 14, 2025 | 00:00 - 08:00
- SGP-DP-H17
- SGP-DP-H23
- SGP-22148
- SGP-22149
- SGP-22150
- ROUTER-02
March 16, 2025 | 00:00 - 08:00
- SGP-25645
- SGP-26635
- SGP-22146
- SGP-22147
- SGP-DP-H36
- SGP-DP-H37
- SGP-DP-H38
March 17, 2025 | 00:00 - 08:00
- SGP-DP-H31
- SGP-DP-H32
- SGP-DP-H33
- SGP-DP-H34
- SGP-DP-B13662
March 21, 2025 | 00:00 - 08:00
- SGP-25663
- SGP-DP-H27
- SGP-DP-H28
- SGP-DP-H29
- SGP-DP-H30
- SGP-DP-H35
March 22, 2025 | 00:00 - 08:00
- SGP-DP-B13160
- SGP-DP-H39
- SGP-DP-H40
We appreciate your patience and will work to ensure a smooth transition. If you have any concerns, please reach out to our support team.